In order to further standardize the management of the region's various types of state-funded engineering and construction projects engineering changes, improve the approval process of engineering changes, to prevent arbitrary changes in the project and over-standard, over-scope, over-investment behavior, and to promote the government's funds are reasonable, lawful, efficient, and safe operation, to ensure the quality of the project to improve the effectiveness of the investment. According to national, provincial and municipal regulations, combined with the actual situation in our region to put forward the following implementation views.
One, the scope of engineering change management
(a) the scope of the region within the scope of various types of state-owned funds for engineering and construction projects, refers to the implementation of the organization by the various levels of administrative organs, institutions, state-owned enterprises, the use of all levels of financial input, government financing, state-owned enterprises and the financing of the project. Inputs, state-owned enterprises own funds and financing inputs, international organizations or foreign governments loans, assistance or donations to invest in state-owned funds in a controlling or dominant position in the project, as well as by the state-owned funds to repurchase the PPP construction projects.
(2) The engineering change referred to in this implementation opinion refers to the following circumstances that occur in the performance of the contract leading to changes in the cost of the project:
1. Cancellation of any one of the work in the contract but the canceled work can not be transferred to the contracting officer or Others;
2. Alter the quality or other characteristics of any of the work under the contract;
3. Alter the baseline, elevation, location, or dimensions of the work under the contract;
4. align: left;">4. Alteration in the time of construction of any of the work under the contract or change in the approved workmanship or sequence of construction;
5. Additional work required to complete the work;
6. Adjustments in municipal planning or governmental decisions, or legal or regulatory adjustments;
6. Adjustment of municipal planning or governmental decision-making, or adjustment of laws, regulations and normative documents;
7. Other circumstances related to the construction of the project that lead to changes in the cost of the project.
Two, engineering change approval and supervision
engineering change approval in principle in accordance with the "Construction Bureau to approve the technical reasonableness of engineering changes and changes in the scope of the Bureau of Finance according to the implementation of funds to change the engineering budget control, administrative approval and approval of the project. Changes in the budget control of the project, the Administrative Approval Bureau to review changes in the project bidding program and change the scope of supervision and audit of the Bureau to monitor the implementation of the project, "the principle of division of responsibility.
Three, engineering change approval process
various types of state-owned funds for engineering and construction projects engineering changes In principle, the implementation of prior approval system, without review and approval shall not be implemented.
(a) engineering changes in the amount of increase or decrease in the amount of product iteration did not exceed the winning bid (including the provisional funds, the same below) of the approval process
1. Project bid price of 30 million yuan (excluding 30 million yuan) or less, the engineering change By the project owner to convene the survey unit (if necessary), design unit, construction unit, supervision unit, construction unit (if any), tracking and auditing unit (if any) and other meetings to determine the implementation. Engineering changes involving structural technology and safety, should be reported to the Construction Bureau to approve the technical soundness of engineering changes before implementation.
2. Project bidding price of 30 million yuan and above, engineering change approval procedures
(1) cumulative increase or decrease in product iteration of the amount of 3 million yuan (excluding 3 million yuan) or less by the project owner of the engineering changes The project owner shall convene the survey unit (if necessary), design unit, construction unit, supervisory unit, substitute construction unit (if any), tracking and auditing unit (if any) and other units to discuss and determine the implementation. Engineering changes involving structural technology and safety, should be reported to the Construction Bureau for approval of engineering changes in the technical reasonableness and then implemented;
(2) cumulative increase or decrease in the amount of product iteration in the 3-5 million yuan (excluding 5 million yuan) of the engineering changes, the project owner to convene the survey unit (if necessary), the design unit, the construction unit, the supervision unit, the agent construction unit The project owner shall apply for the project, and the Construction Bureau shall convene the Administration and Approval Bureau and the Finance Bureau to determine the implementation of the project after the preliminary consultation with the project owner, the supervisory unit, the construction unit (if any), the tracking and auditing unit (if any), etc.;
(3) For the project change of the cumulative amount of increase or decrease of the amount of 5 million yuan and above, for every increase or decrease of 2 million yuan (less than 2 million yuan at the later stage), the project owner shall be required to submit a report to the Construction Bureau for approval and approval. million yuan (later less than 2 million yuan) by the project owner to convene the survey unit (if necessary), design units, construction units, supervision units, on behalf of the unit (if any), tracking and auditing units (if any) and other units of the initial consultation, the project owner to apply for the Construction Bureau convened by the Administration and Approval Bureau, the Finance Bureau and other meetings, the meeting agreed to by the project owner in writing to the management committee to report the changes in the cumulative amount of increase or decrease in the amount of 5-10 million yuan (excluding 10 million yuan) by the management committee in charge of the construction of the leadership approval; cumulative increase or decrease in the amount of 10 million yuan and above by the management committee in charge of the construction of the leadership review and approval and report to the main leadership of the management committee for approval and implementation of the larger amount of money submitted to the director's office of the management committee for finalization.
(ii) engineering changes in the amount of increase or decrease in the amount of product iteration of the adjusted amount of more than the winning bid price (including the provisional sum, the same below) part of the approval process
by the project owner to convene a survey unit (if necessary), the design unit, Construction unit, supervision unit, construction unit (if any), tracking and auditing unit (if any) and other units after the initial consultation in writing to the Construction Bureau to apply for changes, the Construction Bureau after the initial review of the convening of the Administrative Approval Bureau, the Finance Bureau, the consultation agreed to by the project owner unit in writing to the management committee to report on the changes; changes to increase the amount of 1 million yuan (excluding 1 million) by the construction of the management committee in charge of the leadership of the approval of implementation; changes to increase the amount of 1 million yuan (excluding 1 million) by the leadership of the construction Approval of the implementation; changes in the amount of 1 million yuan (including 1 million) by the management committee in charge of the construction of the leadership review agreed to be reported to the management committee director's office and the party committee will be finalized.
(c) the project owner to the management committee to report the change of matters need to include: the content of the change, the reason for the change, the technical approval of the change in the implementation of the program and engineering changes in the approval form (attached).
Project approval procedures are: 1) reported to the Construction Bureau for technical (including the implementation of change program) approval; 2) the project owner will be based on the approved changes in the implementation of the program to send the budget prepared by the Financial Review Center to assess the control price; 3) engineering changes in the approval form (attached to the report of the financial assessment) reported to the relevant departments for approval.
The results of the meetings involved in the above change procedures need to be signed by the relevant departments involved in the written comments.
(d) in the construction of the project due to emergencies requiring the immediate implementation of engineering changes can be made by the project owner, survey units (if necessary), construction units, design units, supervision units, construction units (if any), tracking and auditing units (if any), etc., after consulting and reporting to the Construction Bureau and the management committee in charge of construction of the leadership agreed to implement. Implementation, but need to retain the relevant images and construction data; and in the implementation of the same time in accordance with the above procedures to improve the relevant procedures.
(E) the implementation of the state-funded projects, in accordance with the principle of engineering changes who is responsible for engineering changes in accordance with the implementation of the report for review. Due to survey, design reasons for engineering changes and functional needs of the owner to adjust the construction standards, expand the scope of implementation and municipal planning adjustments or government decision-making adjustments caused by engineering changes, the owner in accordance with the engineering change approval procedures to improve the report approval work. Due to the construction period on behalf of the unit, supervision units or construction units on the national norms adjustments, national and local laws, regulations and policy adjustments, the implementation of the claims, the existence of omissions in the project budget and the amount of engineering volume difference caused by engineering changes, by the unit in accordance with the engineering change approval procedures to improve the approval of the work reported to the approval process.
Four, engineering change approval time
need to be approved by the project owner of the project in turn reported to the relevant departments for review and approval of the relevant departments should be approved within three working days after the approval of the information is complete (seven working days for financial assessment). The relevant departments shall approve the project within 3 working days (7 working days for financial assessment) after the submission of complete information. In principle, major design changes should be reviewed and approved within 10 working days from the date of acceptance after the submission of complete information, in special circumstances can be extended appropriately.
V. Principles of evaluation of engineering changes
(a) by the project owner in accordance with the construction procedures, according to the bidding control price of the pricing specifications, pricing quota, the relevant supporting documents and construction of the current period of the "Sichuan Province, the project costing information". Material prices (the price of materials not on the information using market prices) to prepare the budget, reported to the Finance Bureau for review.
(2) evaluation according to the bidding control price pricing specifications, pricing quotas and related supporting documents, change the construction period of the project, "Sichuan Province, the construction cost information" in the price of materials (information on the price of materials do not use the market price) for the change of the project budget control price evaluation, evaluation of the price of the project as a change in the total cost of control. Control.
Sixth, engineering change involves the principle of settlement of project price
(a) by the original successful bidder to implement the increase in the project, engineering changes to increase the price of the project according to the original construction contract agreed upon the principle of pricing, the original construction contract agreed upon the unclear Adjusted according to the following principles:
1. The successful bidder's bidding price list of quantities of work has been applied to change the price of the project, in accordance with the price of the existing contract price change.
2. If there is no applicable price in the bidder's bill of quantities but there is a price similar to that of the alteration works, the contract price can be altered with reference to the similar price within a reasonable range.
3. If there is no price applicable to or similar to the altered works in the bidder's bill of quantities, the price will be re-grouped in accordance with the principles of valuation of alterations agreed upon in the construction contract;
If no principles of re-grouping of new items are agreed upon in the construction contract or if the agreement is not clear, the price will be re-grouped in accordance with the principles of valuation agreed upon in the construction contract. If the construction contract does not agree on the principle of re-grouping of new items or the agreement is not clear, in accordance with the bidding control price of the pricing specification and pricing quota and supporting documents, changes in the construction of the project during the period of the "Sichuan Provincial Project Costing Information" of the material price grouping and then according to the original bidding down the floating ratio of the downward settlement (which the material price if you use the material price in the tender and the contractor's approval of material price of the material price does not go down, if the material price in the tender is higher than the information price, then use the price of material and the price of material is higher than the information price. If the material price in the tender is higher than the information price, the information price will be adopted and the price will be grouped according to the above principle).
The formula for calculating the downward floating ratio of the original winning bid=1-(the original bidder's evaluation price ÷ the evaluation price of the original bidding control price)
Evaluating the bid price=arithmically corrected bidding price or bidding control price - safety and civilization construction costs - fees - provisional charges - provisional estimate of professional construction costs - provisional estimate of professional construction costs - provisional estimate of professional construction costs - provisional estimate of professional construction costs - provisional estimate of professional construction costs - provisional estimate of professional construction costs - provisional estimate of professional construction costs - provisional estimate of professional construction costs - provisional estimate of professional construction costs Provisional list price - Provisional price of specialized works
4. For the existing list of subheadings in the contract, if the quantity of work increased by the change exceeds the original contract quantity by more than 15% (excluding 15%), and the unit price of the contract for this subheading which has been marked by the successful bidder in the list of works is greater than the price grouped in accordance with the pricing principle as stipulated in Article 6(1)(3), the increase of the quantity of work exceeding 15% or more will be assessed as a result of the change in the price. The volume of work increased by more than 15% of the part of the subhead unit price in accordance with Article 6 (a) of the agreed pricing principles of the third re-correction pricing.
(2) If the original contract corresponding to the change of the work has been marked list of works contract consolidated unit price, there is a serious imbalance in the following cases of quotation, and there is no specific imbalance in the contract has been contracted to amend the pricing of the contract agreed upon, in accordance with the following methods:
1. 50% higher than the corresponding comprehensive unit price of the bidding control price of the project, the price of the project change, the unit price of the price grouping in accordance with the pricing principles of Article 6(1)(3), and the implementation of the original winning price downward fluctuation ratio [calculated in accordance with the formula in accordance with Article 6(1)(3)] settlement;
2. less than 50% lower than the corresponding comprehensive unit price of the bidding control price of the project;
2. When 50% below the corresponding comprehensive unit price of the bidding control price of the project, the price of the project change in accordance with the pricing principles agreed in Article 6 (a) No. 3 above, and then according to the original winning comprehensive unit price and the bidding control price of the project corresponding to the proportion of the comprehensive unit price downward [formula = 1 - (the original winning bidder's consolidated unit price ÷ the original bidding control price of the consolidated unit price)] for settlement.
(c) the original bidding scope of the special increase in the scope of the project can be reported to the Management Committee, re-define the pricing principles.
VII, engineering changes in contract management and acceptance of the completion of management
(a) due to engineering changes require the signing of supplementary contracts and agreements, the original contract has been filed by the signing of the supplementary contracts and agreements in accordance with the procedures of the Construction Bureau for the record, the contract shall not be used as a basis for the settlement of the project without the record. The record of the contract shall not be used as a basis for project settlement.
(2) project completion and acceptance of the project should be a comprehensive check of the completion of the project is in line with the requirements of the approved design documents, without the approval of the project changes shall not be used as the basis for the completion of the acceptance. Changes to the project without the required procedures for approval and unauthorized handling of construction projects must be held accountable and ordered to rectify. Rectification of unqualified projects, the Finance Bureau will not allocate the corresponding part of the construction funds, the relevant departments will not be accepted.
Eight, strict accountability
(a) The engineering regulatory department should strengthen the survey, design, construction, supervision units illegal operation, falsification of the behavior of the law to investigate and punish. For the survey, design, cost consulting and other services unit's own work causes engineering changes over 3% of the winning bid, deducting more than 10% of the contract service fee (the specific amount of each project in the bidding documents clear).
(b) construction units and supervisory departments do not conscientiously fulfill their responsibilities, resulting in engineering changes and adjustments to the budget estimates are not in accordance with the provisions of the supervisory authority to pursue the responsibility of the relevant responsible units and personnel.
Nine, other
This opinion is explained by the management committee of the Luzhou Hi-tech Zone, valid for three years from the date of publication. Engineering changes that occurred before the implementation of this opinion are handled in accordance with the "Luzhou Hi-Tech Zone Management Committee on the issuance of Luzhou Hi-Tech Zone state-owned funds engineering construction project engineering change management implementation opinions (for trial implementation) notice" (Lu Gao Guan Fa [2017] No. 35) document.