Chapter 1 General rules
Article 1 To further standardize the government investment construction projects in the new district of Jiangbei Engineering Change behavior, to ensure project quality, reasonable control of project cost, to ensure the smooth implementation of engineering construction, according to the "Wuhu Municipal Government Investment Project Engineering Change Management Interim Measures" (Wuhu Government Office [2016] No. 12) relevant provisions, combined with the actuality of our region, the development of this provision.
The second This provision applies to all or part of the use of Jiangbei New District government funds investment construction projects.
Article 3 Construction investment projects should be strictly according to the review and approval of the design documents for the implementation of the organization, in principle, unauthorized changes shall not be mutilated to avoid approval of engineering changes. Changes in engineering construction, should be in accordance with the prescribed procedures for reporting, approval, without review and approval of engineering changes shall not be implemented. Approved by the implementation of the change, according to the review of 50% of the price of the progress payment.
Chapter II Change of content
Article IV Change of the project refers to the project from the date of approval of the preliminary design of the project to the date of approval of the preliminary design of the project to the date of approval of the project to the date of approval of the project. The preliminary design of the project from the date of approval to the date of completion and acceptance of the official delivery of the use of the approved preliminary design documents, technical design documents or construction drawings in the implementation of the design documents in the implementation phase of the project scale, technical standards, work content, the number of projects, structural type and so on the adjustment and modification.
Article 5 Engineering changes mainly include the following:
(a) adjustments caused by errors and omissions in the design documents or bill of quantities;
(ii) on-site visas and changes caused by discrepancies between the actual conditions of the construction site and the technical data of the survey report;
(iii) changes to the construction program due to the reasons of the construction unit;
(iv) changes to the construction program due to the reasons of the construction unit;
(d) Changes in important materials and equipment;
(e) Changes in construction works under other circumstances recognized by the competent investment department of the district.
National laws and regulations and policy adjustments, contractual price adjustments of materials resulting in an increase in the cost of the project is not part of the scope of the engineering changes referred to in this approach. The increase in construction cost due to the above reasons shall be implemented in accordance with relevant state regulations and contractual agreements, and shall not be included in the total amount of construction changes. The use of contractual provisional amount into the scope of engineering changes.
Article VI Engineering changes in accordance with the cost of change is divided into general, large, major engineering changes. Changes in the cost of the project construction unit in writing to change the bill of quantities and pricing table data shall prevail.
(a) sub-parts of the change in the cost of less than 100,000 yuan and did not exceed the winning bid price of 5% (inclusive) of the general engineering changes;
(b) sub-parts of the change in the cost of 100,000 yuan (inclusive) more than 500,000 yuan and did not exceed the winning bid price of 5% (inclusive) of the change. More than 5% of the winning bid (inclusive) for large engineering changes;
(c) sub-parts of the change in the cost of 500,000 yuan (inclusive) or engineering changes in the amount of more than 5% over the winning bid for major engineering changes.
Chapter III Responsibility and division of labor
Article VII
Article VII
Project changes are generally led by the construction units Organization review.
Ministry of Industrial Development, Ministry of Finance, Ministry of Planning and Construction for the engineering changes in the review of the fixed participation of the department, the rest of the participating units (departments) by the lead review unit in accordance with the nature of the project and the division of functions to participate in the review of changes in the notification.
The Ministry of Industrial Development is responsible for the guidance, supervision, inspection and review of engineering changes.
The Ministry of Finance is responsible for the supervision of the project investment budget and the review of the cost of engineering changes.
The Ministry of Planning and Construction is responsible for reviewing the bill of quantities and costs of change works, and participating in the review of issues related to engineering changes.
Article VIII Implementation of engineering changes related to the responsibilities of the unit
(a) project construction unit.
The project construction unit referred to in this provision is responsible for organizing the project construction of the responsible unit. Project construction unit as the first person responsible for the management of construction projects, is responsible for effective control of project engineering changes, management, audit and reporting work, is responsible for supervising the implementation of engineering changes to the approval of the implementation of the views of the project is responsible for all types of engineering changes in the information of the ledger organization and management work.
(ii) the rest of the participating units.
Survey and design units are responsible for all types of engineering changes in the survey, design-related work, participate in all types of engineering changes in the audit, and put forward technical advice.
Supervision unit is responsible for the supervision of engineering changes according to the contract, auditing the authenticity and completeness of the engineering change information, and putting forward the audit opinion on the engineering change program and cost, and supervising the implementation of engineering changes.
Construction unit is responsible for the preparation of engineering changes in the implementation of the program and the cost of engineering changes in the budget and other work, according to the approval of engineering changes in the implementation of the views.
Chapter IV Change declaration, review and approval
Article IX Declaration Procedures
(a) the project construction unit shall organize surveying, design units to complete the changes in the construction plan design, and together with the construction and supervision units of the project changes in the program, content, cost and other preliminary examination. After the initial review agreed, the project construction unit in writing, and indicate the reasons for the change.
(b) The project construction unit shall provide the following information:
1. Engineering changes to review the application letter. Application letter for review shall contain the basic situation of the project, the reasons for the change, the responsibility for the analysis and the responsible unit's handling of opinions and recommendations;
2. Project change declaration form signed and stamped by the construction unit project manager, engineering changes in the bill of quantities, the pricing table;
3. align: left;">3. Engineering change parts of the engineering geological survey data, engineering change parts of the original construction drawings and changes in the design, drawings, engineering contact sheets or technical approval sheets, etc.;
4. Larger changes in engineering, the project construction unit should be the necessity of changing the program and economic For demonstration and the formation of minutes, if necessary, should be organized expert demonstration;
5. Bidding documents, engineering changes in the site image picture data, etc.;
6. Other necessary additional information.
Article 10 Review procedures
(a) In addition to general engineering changes, engineering changes will be reviewed by the fixed units and other participating review units to review, if necessary, to invite the relevant experts to participate. Participation.
(2) According to the actual needs of the project construction, the engineering change review will adopt the regular meeting system in principle.
(c) Engineering change review mainly on the application of the need to change the content of the rationality of the review. Need to carry out on-site confirmation, the review unit should be on-site investigation. The amount and price of the declared engineering changes shall be used only as the basis for grading management, and the final result of the price review of the completion settlement shall prevail, and the result of the price review of the completion settlement shall be no more than the declared amount. Pricing principles in accordance with the project bidding documents, contractual agreements and relevant provisions of the municipal government.
Article XI Approval process
(a) the lead unit of the review shall be accepted on the date of the application for change, the organization within five working days to review. Participate in the review unit (department) review comments should be reviewed within 2 working days after the meeting back to the review lead unit, the review comments shall be signed and stamped by the unit (department) responsible for the main comrade. Review unit (department) more than half (including) do not agree, the change is not recognized.
(2) for the review unit (department) on-site confirmation and review of the engineering changes adopted by the project, the need for project construction units to re-review or additional information, the project construction unit should be improved in a timely manner. After the change of information is complete, the lead review unit within three working days to issue a summary of the review of changes.
(C) the implementation of hierarchical management of engineering changes.
General engineering changes: the project construction unit is responsible for the review and validation.
Larger engineering changes: the project construction unit to organize a fixed participating units (departments) will be reviewed, and the results of the review will be reported to the management committee in charge of the finalization of the leadership.
Major engineering changes: the project construction unit to organize a fixed participating units (departments) will be reviewed, the review results reported to the management committee in charge of the leadership review, the project construction unit reported to the director of the management committee will be finalized.
(d) In order to strictly control engineering changes, the total amount of changes in each sub-section exceeds 5% of the winning bid, all engineering changes (including the part that has been reviewed) need to be submitted to the Office of the Director of the Commission to change the description.
Article XII After the end of the review of engineering changes, the project construction unit to improve the engineering changes in the information reported to the Ministry of Finance for the record, and retain the engineering changes in the construction of video images and other information.
Chapter V Related Requirements
Article XIII For natural disasters encountered in emergency situations, or When there is a danger to persons, major property safety and force majeure events, it may be implemented according to the relevant provisions of the emergency rescue works. The construction unit shall, within 15 working days from the date of the event, make up the relevant procedures in accordance with the provisions of this regulation.
Article XIV All projects without review or changes in accordance with the prescribed procedures are not recognized. Will review the project through, in principle, not again change; will review the project did not pass, may not be proposed for reconsideration or other reasons again. It is strictly prohibited to split the changes to declare.
Article 15 Projects in the implementation of the process of planning adjustments need to be made by the Ministry of Planning and Construction is responsible for the relevant planning adjustment procedures, and will be the relevant approvals and other information delivered to the project construction unit. The project construction unit in accordance with the provisions of the change to fulfill the reporting procedures.
Article XVI Engineering changes involving major program changes and budget adjustments, the project construction unit needs to be major program changes reported by the management committee after the finalization of the Office of the Director, in accordance with the relevant requirements by the Ministry of Industrial Development to adjust the budget estimates. The Audit Center in due course of sampling changes in the project, the legality of the whole process to carry out audit supervision.
Chapter VI Accountability
Article XVII Project construction units in violation of the provisions of this. Engineering changes without review, review procedures are not in place or the implementation of the first after the review, the Ministry of Industrial Development shall not adjust the budget estimates, the Ministry of Finance shall not recognize the relevant costs caused by the changes in the handling of project payment and settlement of the project price.
Article 18 In accordance with the principle of first accountability, after the change, any unreasonable changes caused by non-objective reasons, the relevant departments should first put forward the views of accountability before the change.
Article 19 Due to the survey, design unit responsibility for engineering changes, with reference to the "Construction Engineering Survey and Design Management Regulations" and the relevant provisions of its punishment.
Because of engineering changes caused by the responsibility of the bill of quantities compilation and review unit, the project construction unit shall be in accordance with the project engineering consulting bidding documents agreed upon in the corresponding provisions of the bill of quantities compilation and review unit of the breach of contract responsibility.
If the engineering changes are caused by the responsibility of construction and supervision unit, the construction unit and supervision unit shall bear the responsibility themselves.
The cost of engineering changes caused by the survey, design, bill of quantities compilation and review, construction and supervision units exceeds 5% of the winning bid (contract price), and the construction unit of the project shall, according to the size of the responsibility, the loss caused by the cause of the situation, put forward the processing opinions based on the relevant laws and regulations and submit them to the Management Committee for approval.
Article 20 Project construction units, construction units, supervision units, design units, survey units, engineering cost consulting units to collude with each other, take false means of obtaining illegal benefits, deal with in accordance with the law.
Article 21 Review unit staff in the engineering change review process there is an abuse of power, dereliction of duty and seek improper advantage, etc., in accordance with disciplinary rules and regulations.
Article 22 This provision is responsible for the interpretation of the Ministry of Planning and Construction.
Article 23 These measures shall come into force on the date of publication.The "Management Provisions for Engineering Changes (Visa) Work of Construction Projects in Concentration Areas (Interim)" (Jiangbei Management Secretary [2018] No. 28) issued on November 30, 2018 shall be repealed at the same time.