In order to conscientiously implement the "General Office of the People's Government of Anhui Province on the issuance of the creation of an optimal business environment benchmarking and enhancement initiatives (2023 version) of the notice (Anhui government office secret [2023] 11)," "on further improvement of electric power access engineering "zero investment" to create a first-class business environment notice" (Anhui Development and Reform Price Letter [2022] 93) and other documents. [2022] No. 93) and other documents, according to the "Wuhu City Development and Reform Commission and other units on the issuance of & lt; Wuhu City, comprehensively enhance the "access to electricity" level of service to do a good job of electric power access project "zero investment" implementation rules & gt; notice" (Wuhu Development and Reform) Price [2023] No. 255) (hereinafter referred to as "implementation rules") requirements, combined with the actual development zone, the development of this approach.
I, business acceptance
Enterprises according to the actual demand for electricity, the power supply sector to submit an application for telegraphic installation, the power supply sector needs to be completed within one working day to accept the confirmation.
Second, the program response
(a) power supply departments need to receive the enterprise to submit the telegraph installation application within three working days to carry out door-to-door survey services, based on the "electric power user technical specifications for the expansion of the installation of power users" (DL/T1917-2018) and other relevant national and industry norms and provisions of the integrated grid planning, electricity demand and local power supply conditions and other factors to determine the power consumption enterprise access program, and complete the program response within the time limit set by the National Energy Administration.
(2) According to the Implementing Rules, it is determined that the Sanshan Economic Development Zone Management Committee is responsible for investing in the power access project, the power supply department needs to synchronize the power supply response letter program submitted to the Economic Development Bureau for the record.
Three, categorized implementation
(a) Electricity access works directly related to the reserve land.
According to the unified planning, belonging to the Sanshan Economic Development Zone Management Committee reserve land directly related to the power access project, by the Sanshan Economic Development Zone Management Committee will be included in the cost of the power access project land reserve project investment estimates and the organization of the implementation of the relevant costs according to the ownership of the reserve parcels into the cost of the land resumption in accordance with the relevant provisions of the assumption.
(2) Other types of power access works.
1. Government investment projects. Led by the responsible unit of the project, the project unit is responsible for the specific implementation of its power access project costs included in the project engineering and construction costs, according to the provisions of the construction of the source of funds to bear.
2. Enterprise investment projects. According to the Implementing Rules, belonging to the Sanshan Economic Development Zone Management Committee to implement the power access project, the enterprise and the Economic Development Bureau for docking, the Economic Development Bureau to coordinate the key project construction management office, the key project construction management office in accordance with the procedures.
Four, engineering investment
(a) direct investment.
1. According to the actual situation of the enterprise and the project, Sanshan Economic Development Zone Management Committee Economic Development Bureau to implement the lead unit, the implementation of units, the implementation of the unit in accordance with the prescribed procedures to carry out timely design of the grid supporting drawings and the preparation of estimates (budget), the organization of the estimates (budget) of the preliminary audit, the results of the audit is confirmed by the arrangement of the funding plan. If the project's electricity demand changes at a later stage, the estimate (budget) audit should be re-conducted.
2. If the enterprise and the project in the implementation of the document, has completed its own construction of the relevant power access works. By the Economic Development Bureau of the first audit, belonging to the Sanshan Economic Development Zone Management Committee within the scope of implementation, the Financial Services Bureau in conjunction with the Economic Development Bureau in accordance with the relevant provisions of the selected third-party auditor, should be implemented by the Sanshan Economic Development Zone of the electric power access project to conduct an audit, and according to the audit report to arrange funds for payment.
(ii) Commissioning.
According to the "14th Five-Year Plan" Power Grid Development and Construction Cooperation Framework Agreement signed by the Management Committee of Sanshan Economic Development Zone and State Grid Wuhu Power Supply Company, the power access project to be implemented by the Management Committee of Sanshan Economic Development Zone can be entrusted to the power supply department to build on behalf of the construction by signing a commissioning agreement to build on behalf of the construction of the agreement on the scope of the project, the duration of the project, the funding process and mode of payment and the responsibilities of both parties. Payment process and mode and the responsibility of both parties, etc. to implement, to be issued by the third-party auditor audit report, to complete the process of payment of funds.
V. Funding Settlement
The financial sector should arrange funds according to the direct investment related to the project, based on the audit price, and timely payment; entrusted to the power supply company to build the project, the power supply company should ensure that entrusted on behalf of the construction of the funds for the exclusive use of the funds, shall not be misappropriated, mixed with the project funds, the financial sector should be paid in accordance with the agreement; the settlement of funds need to be based on the classification of electric power access project corresponds to the settlement; all payments should be made according to the classification of electric power access project. Settlement; all payments should be included in the management committee to obtain electricity "zero investment" special funds for statistical summary.
Sixth, the relevant requirements
(a) power supply departments in the implementation of the project on behalf of the construction process, the construction project should be included in the grid project homogenization management, project quality supervision and progress control, to ensure that the project is completed in accordance with the agreed time schedule.
(2) the towns and streets are responsible for the jurisdiction of the enterprise new installation (capacity increase) project power corridor access, green compensation and other issues of coordination.
(3) by the Sanshan Economic Development Zone Management Committee to invest in the construction of the power access project should be built according to the standard can be transferred to the power grid, after completion of the asset transfer to the power supply sector, the subsequent operation, maintenance, updating and renovation costs of the power supply sector is responsible for.
(D) special areas or can not be specified, in accordance with the "one issue at a time" principle, by the enterprise or project leader, the coordinated carrier units, the Economic Development Board, the power supply sector, such as negotiation and confirmation.
Seven, bylaws
(a) the implementation of this approach in the process, in the event of national, provincial and municipal major policy adjustments, according to the actual situation in due course.
(2) These measures shall be implemented from the date of issuance, and shall be interpreted by the Economic Development Bureau in conjunction with the relevant departments.