Qinhuangdao Economic and Technological Development Zone Key Projects and Enterprises Management Measures
2023-09-29 00:00

Chapter I General Rules

Article 1 To further enhance the key projects and enterprise management system, standardization, refinement level, to grasp the key project construction and enterprise service work, fully stimulate the momentum of the market, according to the "Optimization of Business Environment Ordinance" and the provincial and municipal "key project management approach" and other relevant provisions, combined with the actual development zone

Second development zone of the national, provincial and municipal key projects in the organization, scheduling management, service guarantee, supervision and assessment and corporate services and other work applicable to this approach.

Article 3 The key projects referred to in this approach refers to the implementation of the development zone, in line with the national, provincial and municipal major strategies, development planning, territorial spatial planning, industrial policy, industry norms and high-quality development of various types of projects, mainly including infrastructure projects, industrial projects, real estate projects. The enterprises referred to in these measures refer to all kinds of market entities registered in the development zone.

Article 4 Key projects are divided into key promotion projects, key projects under construction and technological transformation projects. Enterprises in accordance with the type of industry is divided into new energy and high-end intelligent equipment manufacturing, automobiles and parts, grain, oil and food deep processing, precision electronic information technology and intelligent fire, rehabilitation aids and medical health, modern service industry and other 7 categories.

(a) the key to promote the project is from the investment intention to complete the construction permit procedures and the use of the original plant to obtain construction permits for new plant projects, the stage of the project service management by the Investment Promotion Bureau to take the lead.

(2) the key projects under construction refers to the construction permit to the completion of the project to put into operation, the project service management at this stage is led by the Economic Development Bureau.

(c) Technological reform projects refer to projects that simply acquire equipment, and the management of such project services is led by the Bureau of Industry and Emergency Management.

(D) enterprise package work by the Industry and Emergency Management Bureau to take the lead.

Chapter II Declaration and determination

Article 5 Investment scale of 20 million yuan and above the government investment projects and enterprise investment projects are included in the scope of key project management. The previous year's statistical data as a benchmark, "four enterprises" into the leadership and departmental package category.

(a) the key to promote the project, including planning reserves, key in the talks and complete the approval of the project for the record approval, should be consistent with the national, provincial and municipal major strategies and industrial policies and other requirements.

(ii) the key projects under construction by obtaining construction permits to promote the transformation of key projects. Has been included in the previous year's list of key construction projects for the continuation of the project, in addition to have been completed or terminated construction, in principle, automatically carried over to the next year's list of key construction projects.

(C) key projects under construction after completion and acceptance, the expected annual output value, revenue to reach the "four on the enterprise" standard to the enterprise package service.

(d) has been included in the national, provincial and municipal development planning, regional planning, special planning and national major project database and meet the reporting requirements of the project, priority as a key project.

(E) at the beginning of each year, the Industry and Emergency Management Bureau based on statistical data, to determine the inclusion of the leading departments to link enterprises.

Article VI key projects and enterprise library dynamic management.

(a) Administrative Approval Bureau is responsible for the new weekly filing, approval and approval, obtaining construction permits for the project pushed to the Investment Promotion and Investment Promotion Bureau, Economic Development Bureau, Industry and Emergency Management Bureau. Based on the actual situation of the project, respectively, into the focus on promoting, focusing on the construction and technological transformation project library management.

(ii) Investment Promotion Bureau, Industry and Emergency Management Bureau according to the project demand, against the national major projects and provincial and municipal key projects reporting standards, the project approval progress, investment scale, start time and the implementation of construction conditions, such as review, and monthly reported to the Bureau of Economic Development in accordance with the relevant provisions of the project management, to apply to the higher level into the national major projects or provincial and municipal key projects.

(3) key projects completed and put into operation, the Economic Development Bureau is responsible for its transfer from the key project library, the Industry and Emergency Management Bureau based on relevant criteria to determine whether to include the scope of the enterprise package.

(4) For projects or enterprises that cannot be continued or do not meet the reporting requirements of key projects and are not included in the scope of the package due to the impact of national macro-control, adjustment of industrial policies, major changes in construction conditions, force majeure and other factors, the projects or enterprises will be transferred out by the Investment Promotion Bureau, the Bureau of Economic Development, and the Bureau of Industry, Information and Contingency Management, respectively, after the initial examination and reporting to the Public Works Committee and the Management Committee for approval.

Article VII At the beginning of each year, Investment Promotion and Investment Promotion Bureau to form a key to promote the annual list of proposed projects, Economic Development Bureau to form a list of key construction projects annual list of proposals, Industry and Emergency Management Bureau to form a technological reform projects, the annual list of proposals for the package of enterprises, reported to the Work Committee, the Management Committee agreed to the first quarter of the year issued in the annual package of plans.

Chapter III Service Guarantee

Article VIII Deepen the leadership and departments of the package of key projects and enterprises mechanism, since the signing of the key projects, a clear package of leaders, package of departments and package of people, investment of more than 500 million yuan of the project by the package of departments to take the lead in the establishment of the work of the task force. For project units and enterprises to provide efficient and high-quality services, around the current state of enterprise development and project characteristics, the establishment of supply chain blocking points, breakpoints ledgers, research solutions, one by one to solve the problem, and effectively crack the outstanding problems restricting the construction of the project and the production and operation of enterprises, and to promote the project to put into production early, the healthy development of enterprises.

Article IX Strengthen the key project land security, support the implementation of the "standard land" concessions, accelerate the promotion of regional assessment, improve the efficiency of land allocation. Urban and rural construction management committee to co-ordinate the annual new land use plan indicators, focusing on guaranteeing the construction of key projects land demand.

Article 10 Key projects require energy indicators by the Economic Development Bureau to be guaranteed to enhance the flexibility of the total energy consumption management, focusing on support to protect the unit of energy consumption of the economic output of the project with significant benefits. Actively strive for key projects into the national and provincial major projects in energy consumption alone.

Article XI Key projects require pollutant emission targets to be guaranteed by the Ecological Environment Bureau, the part of the shortfall in meeting the requirements for improvement of environmental quality under the conditions of guidance to enterprises to dig deeper into their own potential for emission reduction and coordination to solve the problem.

Article XII The government investment projects included in the list of key projects, the Finance and Economics Bureau should be based on the progress of the project to ensure timely disbursement of project funds. Finance and Finance Bureau at the beginning of each year should be arranged in the financial budget for key projects in the preliminary work, mainly for key projects planning and planning programs, project proposals, feasibility study reports, preliminary design and other materials preparation and review fees and other costs directly related to the project's preliminary work.

Article XIII For the inclusion of key projects in the library of the project and the inclusion of the scope of the package of enterprises, through the Economic Development Bureau, Finance and Finance Bureau to establish a long-term mechanism for financing docking, timely promotion to financial institutions, encourage and guide financial institutions to innovate financial services and products, to broaden the channels of enterprise financing, to ensure that the key project funding needs.

Article XIV The Urban and Rural Construction Management Committee, led by the power supply company, Taisheng Water Company, Taisheng Power Company, Taisheng Gas Company, communications operators and other units with the cooperation, should actively protect the key construction projects and enterprises in the construction and production of electricity, transportation of materials, water, heat, gas and communications needs.

Article 15 Administrative Approval Bureau, Urban and Rural Construction Management Committee and other departments should be based on relevant laws and regulations, in accordance with the "simplify the approval, optimize the process, time-bound" principle, to guide the project unit to accelerate the fulfillment of the key project planning and land use, project planning, environmental impact assessment, safety assessment, evaluation of the use of energy, Construction permits and other approval procedures, and promote the early commencement of the project.

Article XVI Economic Development Bureau, Science and Technology Innovation and Big Data Management Bureau, Industry and Emergency Management Bureau and other departments to fully publicize the interpretation of various types of policies at all levels to benefit enterprises, focusing on the key innovation short boards and technological needs of enterprises, the release of the policy dividend-oriented, co-ordinate the promotion of key areas of basic research, the key common technology research, high-energy innovation platform construction, scientific and technological achievements, such as the transfer of the work The work to enhance enterprise innovation capacity, break through the key technological bottlenecks, and enhance the endogenous momentum of industrial development.

Chapter IV scheduling management

Article XVII the package of departments and project units and enterprises to establish regular working contacts, weekly in-depth research visits, multi-angle, all-round understanding of the project and business conditions and needs, smooth information feedback channels, at any time to collect the project and the views and suggestions, timely coordination and processing. The leader of the package to listen to the package every week to report on the work of the department, the constraints on the project to promote the development of enterprises to coordinate the scheduling of the problem.

Article 18 Merchants and Investment Promotion Bureau, Economic Development Bureau, Industry and Emergency Management Bureau, the weekly feedback on the package of departments need to be coordinated by the Work Committee, the management committee to solve the problem of combing and summarizing, to bring to the management committee to convene a half-monthly scheduling meeting, the work of the Committee held a monthly scheduling meeting, focusing on coordinating and solving the process of promoting the project and the development of enterprises in the major problems.

Chapter V Supervision and assessment

Article 19 Investment Promotion and Investment Promotion Bureau based on the investment agreement on the completion of the commissioning of the project after 2 years of assessment of the project, the project did not fulfill the investment agreement agreed matters proposed rectification, submitted to the Public Works Committee, the Committee for consideration.

Article 20 key projects and enterprises to implement weekly analysis, monthly briefing, quarterly summary, annual assessment system. The better the completion of the work of the department, in particular, the main person in charge of the department often in-depth project line, to help coordinate the solution to the problem, to be assessed plus points; the completion of the poorer departments, in the assessment of the corresponding points deducted. For two consecutive monthly rankings of the bottom of the department, to submit to the Discipline Inspection and Supervision Work Committee for an interview and urge rectification.

Article 21 led by the Party Work Department, Economic Development Bureau, together with the Investment Promotion and Investment Promotion Bureau, Industry and Emergency Management Bureau, is responsible for each year to promote the effectiveness of the departments of key projects and enterprises to package the effectiveness of the work of the comprehensive classification assessment, and the results of the assessment will be included in the departmental leadership of the annual comprehensive assessment.

Sixth chapter attached then

Article 22 This approach shall come into force on the date of issuance, valid for three years.

Article 23 Comprehensively implement the national, provincial and municipal support policies, in accordance with the principle of "from the high and not repeated" to support market players.